Hawthorne Station enters Phase 2 of its redevelopment on Monday, August 5. Hawthorne Station will remain open during construction and all bus operations will continue uninterrupted.

The North Parking Lot and West Parking Lot are now open for employee and public use.

  • The North Parking Lot is expected to have periodic closures into mid-August as work continues.
  • Please, no overnight parking and watch for closure notices each morning.

The North Bus Platforms (marked “A” on the diagram) remain closed pending installation of bus shelters.

The alley behind Hawthorne Station including the driveway on 4th Street (marked “B” on the diagram) are closed until mid-August. These areas are being resurfaced, with ADA crosswalks and improved sidewalks being added.

  • No pass through traffic will be allowed during this closure. The alley remains open for business access east of the work area closure.
  • Though access will be provided for pedestrians on 4th Street, they are asked to use 3rd Street during this closure.

 

Diagram of Hawthorne Station construction areas
Phase 2 closure areas in red.

Half of the South Lot (marked “C” on the diagram) is closed until the end of August.

  • No pass through traffic will be allowed during this closure.
  • This area is being resurfaced to create additional bus platforms, bike parking, and new shelters.

The half of the South Lot accessed from Hawthorne Ave (marked “D” on the diagram) will remain open during Phase 2.

  • ADA parking is available in this area.
  • The Hawthorne Station lobby and restrooms are accessible from this area.
  • Please watch for buses and pedestrians on Hawthorne Ave when using this driveway.

Once Phase 2 is complete and all of the areas marked A, B, and C are open, then area D will close for construction. Phase 3 of construction will begin in area D only once all the areas affected in Phase 2 are complete and reopened. The current estimate is September.